The first of three new sets of high voltage electricity cables connecting Dinorwig hydroelectric power station in Gwynedd to National Grid’s transmission network has been energised.
Engineers from National Grid, and contractors Morgan Sindall Infrastructure and Siemens Energy, reached the key milestone as part of the Dinorwig to Pentir project to replace cables originally installed in the 1970s, and which are now coming to the end of their operational life.
Dinorwig power station is owned and operated by First Hydro, a company which is 75% owned by ENGIE.
Since autumn 2021, National Grid has been upgrading the 12 km connection between its 400 kV Dinorwig substation – which sits inside the same mountain as the power station, transmitting its electricity to the grid – and its 400 kV Pentir substation.
The first new circuit, comprising three 12.2 km cables each made from 14 sections joined together and weighing an estimated 1500 t, has been installed under sections of the A4086 and A4244, in nearby fields and inside Dinorwig.
Each new circuit takes a different route from the original cables, ensuring the existing connection can remain in service and continue transmitting vital clean power from Dinorwig while the upgrades take place.
National Grid’s project is a necessary upgrade to the transmission network to ensure the reliability and security of electricity supplies from ENGIE’s First Hydro site to the local area and beyond in the decades to come, as demand for electricity rises. Work is ongoing to complete two other new circuits as part of the scheme.
Alongside installing the new underground electricity cables, National Grid is also making good progress on major upgrades to its Dinorwig substation.
While the project is hidden from view within the mountain, the complex engineering work is an equally essential part of creating the new, secure, and reliable connection between the power station and the electricity network.
Phil Rose, National Grid’s Lead Project Manager for the Dinorwig to Pentir cable replacement project, said: “Completing the first of our three connections marks a really significant milestone in this crucial project to futureproof the infrastructure carrying clean power from Electric Mountain.
“It’s also a fantastic achievement for the team despite some very difficult conditions, with extremely hard rock and unprecedented rainfall challenging our progress at times.
“We appreciate the cooperation and understanding of the local community whilst the work takes place, and want to thank everyone locally for their continued patience while this essential work progresses.”
Peter Kirk, Managing Director – Energy at Morgan Sindall Infrastructure, added: “Energising circuit 3 at Dinorwig-Pentir creates a more resilient power network for the UK. This improvement will enable the network to better handle sudden changes in power demand and unexpected outages, and also supports the UK’s net-zero carbon goals by providing vital infrastructure needed for renewable energy sources.
“The project’s success is only possible because of close collaboration between National Grid, Morgan Sindall Infrastructure, and the other project partners. Thank you and congratulations to everyone involved.”
Delphine Cherel-Sparham, Managing Director of ENGIE Flexible Generation UK, concluded: “As owner and operator of Dinorwig power station, ENGIE is excited to see the first new high voltage cables energised as part of the Dinorwig to Pentir project.
“This milestone is key to futureproofing our infrastructure and ensuring that the clean energy from Dinorwig continues to power communities across the UK. The collaboration between project partners and the First Hydro team has been essential to the successful and safe delivery of this project.”
As part of its work at Dinorwig, National Grid is also safeguarding critical bat habitats in the cable tunnels, which has included installing permanent acoustic barriers alongside roosts to reduce disruption during construction.
Dinorwig hydroelectric power station is made up of 16 km of underground tunnels deep below Elidir Fawr mountain in Gwynedd. It is a vital part of the electricity network in Wales and England, providing fast-response power generation to help stabilise demand on the transmission network.
For more news and technical articles from the global renewable industry, read the latest issue of Energy Global magazine.
Energy Global’s Winter 2024 issue
Don’t miss out on our last issue of the year! The Winter issue of Energy Global is out now; this issue kicks off with a guest comment from Veronica Maxted, Director of Renewables at RS Group before moving on to a regional report on the current state of the renewables industry in North America. This edition of the magazine also explores key topics such as inspection and maintenance, solar optimisation, energy storage technology, geothermal drilling and operations, and much more. With contributions from key industry leaders such as Viridien, Hexagon, DNV Energy Systems, and Halliburton, among others, dive into the issue and see what you could learn.
Read the article online at: https://www.energyglobal.com/other-renewables/11032025/national-grid-connects-dinorwig-hydropower-station/
#National #Grid #connects #Dinorwig #hydropower #station